Plan Review Exemption
Under OAR 333-061-0060(4)(a) (PDF), water suppliers may request plan review exemption for water main extension projects. Practically speaking, this means that water systems with plan review exemption do not need to submit plans and fees for water main extension projects.

Qualifying for exemption
In order to qualify for exemption, water systems must:
  • Have a current master plan that has been reviewed and approved by Drinking Water Services (Note: community water systems with 300 or more connections are required to maintain a current master plan. Community water systems with less than 300 connections can still qualify for the exemption if they have a current master plan.)
  • Certify that any future water main extensions will be carried out in conformance with construction standards (OAR 333-061-0050, PDF). This means that the water system must have an Oregon Professional Engineer on staff or under contract to provide engineering services for the entire duration of the project; and
  • Certify that they have staff qualified to effectively supervise the projects.
Requesting exemption
In order to request an exemption, the water system must submit a letter detailing how the water system meets the required qualifications. The letter must be signed by the engineer of record for the water system.

Maintaining exemption
In order to maintain the exemption, an annual project summary for the previous year must be submitted to Drinking Water Services by January 31st via either mail or email. The annual project summary must include a list of water main projects signed by the engineer of record for the water system. This summary is required to contain the following information:
  • Project title (ex: "Main Street Water Main Extension");
  • Type and size of pipe installed;
  • Length of pipe installed (in linear feet); and
  • A statement that certifies that construction was carried out in conformance with construction standards (OAR 333-061-0050).
If no water main extensions were completed for the previous year, a statement to that effect must be submitted by the engineer of record.

Failure to submit the summary of projects in a timely manner may result in the water system losing plan review exemption for water main projects.

Limitations
Note that plan review exemption for water main extensions does not apply to other infrastructure projects such as sources of supply, treatment facilities, or reservoirs. Plans and fees are still required for these projects, according to the information on the Requirements & Resources page.